High above the Intracoastal Waterway, on top of what was once dubbed the
"bridge to nowhere," members of the public today joined with government
officials, highway engineers and craftsmen to participate in the
official opening and dedication of the $386 million Conway Bypass
highway project in South Carolina, some 17 months ahead of schedule.
The project's first segment, which includes the Billy Alford Bridge upon
which the ceremonies took place, runs from Highway 17 to Highway 90,
linking North Myrtle Beach to Conway, representing one-third of the
project's eventual total 28.5-mile route. In addition to easing traffic
congestion, the new highway will provide a second major evacuation route
during hurricanes.
Officials from Fluor Daniel, the engineering and construction unit of
Fluor Corporation (NYSE: FLR), which is managing the project, the South
Carolina Department of Transportation (SCDOT), and Horry County hosted
the dedication.
"On behalf of the citizens of South Carolina and the Department of
Transportation, I am proud to dedicate this important and invaluable
addition to our state highway system," said Elizabeth Mabry, executive
director of SCDOT. "This first segment offers just a small glimpse of a
much larger and much brighter future concerning the modernizing and
upgrading of our highway systems both here and throughout South
Carolina."
Mabry also cited the project as an example of how the public-private
partnership process can benefit the citizens of South Carolina. Conway
Bypass is the first design-build project of South Carolina's
Partners-in-Progress Program that was designed to accelerate the
completion of five significant projects within the state.
"We are proud to be a major part of this very important building
program," said Ron Oakley, president of Fluor Daniel's Infrastructure
Unit. "No longer can anyone call this the 'bridge to nowhere' because,
as of today, it's the 'bridge to somewhere,' and for that the citizens
of this state can thank the visionary leadership of SCDOT, the South
Carolina General Assembly, the RIDE program and many others who saw a
need and acted to make it a reality."
Among those cited by Oakley as instrumental in the construction of the
project was Billy Alford, a former highway commissioner for whom the
project's first of 31 bridges was named. Alford, who attended today's
ceremonies, was credited by Oakley and others as having "the courage to
support construction of the project in the face of unwarranted criticism
that stalled the project for three years."
"Without his ability to convince his fellow commissioners of the need
for completing this vital new highway, it is doubtful we would be
standing here today dedicating anything," said Oakley. "The citizens of
the state and of this locale owe a debt of gratitude to Billy Alford."
According to Oakley, the entire project team devoted "a tremendous
amount of financial and personnel resources" to accelerate the progress
on the project, which brings an additional means of egress from the
Myrtle Beach area significantly earlier than expected. Project team
members managed by Fluor Daniel include design, construction and quality
control organizations.
Design team members included Davis & Floyd, The LPA Group, and FIGG
Engineers. The construction team was comprised of CP & J, A.O. Hardee,
Willis Construction Company, RECCHI America, Traylor Brothers, APAC
Carolina and APAC Georgia United Contractors. Responsible for quality
control were the LawGibb Group and S&ME. Land acquisition was handled by
PAN, Inc.
Despite facing three major hurricanes during construction of the first
segment, the project team implemented a recovery schedule that allowed
for the early completion of what Oakley termed "this first and vital
link," which will now allow an additional route from the Grand Strand
during evacuations.
Construction of the project continues with work on the remaining
segments. Plans call for the entire highway to be completed prior to
December 2001, which will link North Myrtle Beach at Highway 17 to U.S.
Route 501 in Conway. The nearly 30-mile route will include 31 bridges
designed to traverse and protect some 300 acres of environmentally
sensitive wetlands. Special methods of construction were utilized by
Fluor during the installation of piles supporting the roadway and
bridges, which will total more than 5,000 upon completion. This included
raised track-like platforms, or trestles, that allowed heavy cranes to
traverse work corridors without coming into contact with, or otherwise
damaging, wetland areas.
With 1999 revenues of $12.4 billion, Fluor Corporation provides services
on a global basis in the fields of engineering, procurement,