Fluor Daniel announced today it has been selected by Southern Peru Ltd.
(SPL) to provide services for the expansion of its Cuajone copper
concentrator project in Southern Peru. Total project cost is estimated
at $285 million; Fluor Daniel’s contract value is $157 million.
Fluor Daniel’s Mining & Minerals operating company is providing
engineering, procurement and construction services. SPL’s modernization
and expansion program of the Cuajone mine and concentrator will be
achieved in two phases, increasing concentrator throughput from 64,000
standard ton per day (stpd) to 154,000 stpd. Employment is expected to
peak at 1,000, and the first phase to 90,000 stpd is targeted for
completion by the end of 1998.
"Fluor Daniel is pleased to have been chosen by SPL to undertake this
expansion project," said Phil Asherman, president of Fluor Daniel’s
Mining & Minerals operating company. "Having worked on the initial
Cuajone copper complex in 1975, we have a long-standing interest in
continuing our association with SPL at Cuajone."
SPL is owned by ASARCO (54 percent), the Marmon Group (22 percent) and
Phelps Dodge (16 percent), with the remaining 8 percent of the company
stock held on the U.S. and Lima stock markets. SPL operates two mines,
concentrator facilities, a copper smelter and refinery in the south of
Peru.